CPM Computations
In the Open Standard
Shah. HBMember for 17 years 10 months
- Created
- 4
- 2
0
Hi to all
Which option does software use for CPM computations {Considering Forward Pass alone }
Option 1 EF = ES + D − 1.
Option 2 EF = ES + D.
Is there any advantage in selection ?
As both gives the same result on work out.
All comments form seniors are more appreciated
Which option does software use for CPM computations {Considering Forward Pass alone }
Option 1 EF = ES + D − 1.
Option 2 EF = ES + D.
Is there any advantage in selection ?
As both gives the same result on work out.
All comments form seniors are more appreciated