Arun VasanthMember for 17 years
Created
5
3
0
Dear Friends
Iam Working on the master program of a 45 storey tower.
Some items I am confused about the relations for procurement & activities...
I will write down the activites dear friends please give me the link by considering the tower project...

1.Aviation system ( Air craft warning light)
2.Access control system
3.Building management system
4.Telephone & Data system
5.Public adress system
6.CCTV system
7.Fire alarm system
8.Sanitory fixtures
9.Pumps
10.Water heater
11.Fans & blowers
12.Lighting fixtures
13.Generators
14.Switches & sockets
15.Chilled pressurisation units
16.Fancoil units
17.Air Handling units
18.Chiller units
19.Water feature works
20.Hard & Soft Land scaping
21.canopy works
22.Signage works
23.Road marking
24.Traffic barrier system
25.Structural steel works


Please help me friends to accomplish the program...

you paste the quiries in excel & make the links
& relations
please send it to arunsiar@hotmail.com


With regards
Arun Vasanth

5 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Arun

    For all MEP systems there are a number of key construction stages that have to be linked to the MEP tasks.

    So for EACH and EVERY system set up the following START milestone linked to the structure.

    1. Construction ready for placement of kit.
    2. Safe working zone for ceiling and floor zone horizontals.
    3. Riser cases built & weather tight

    Then add the relevant tasks.
    1. Install kit
    2. Install ceiling horizontals then floor horizontals in the following sequence:
    2.1 Ducting
    2.2 Piping
    2.3 Cable trays and containment
    2.4 IT supports
    3. Install systems in risers - using the same sequence
    4. Install connection from Kit to Risers
    5. Connect risers to horizontals
    6. When weatertight pull cables from kit to switchboard
    7. When ceiling gris is installed connect to service tiles
    8. When foor grid is installed connect to service tiles
    9. When partitions are in place install vertical conuits and boxes
    10. When ready go back and second fix
    11. When power and other services are connected and all systems are closed up start commissioning for each level - allow 5 working days
    12. When all level tests are complete and no other trades are in the structure start project commissioning - allow at least 30 working days

    As far as landscaping work is concerned they can only start when:

    1. The scaffolding is down
    2. Access and storage areas are minimised

    This will allow the main areas to start - you will need a final section once your site is clear of all cabins and temporaray access roads are removed.

    Best regards

    Mike Testro
  2. 0
    Richard Spedding ·
    Arun

    Very sound advice from Mike. However you will also need to consider on a 45 storey tower.

    What levels are the intermediate M&E plant rooms and which floors do they serve.

    Is it proposed to use prefabricated modular riser systems (I would recommend this) and how big are they - how many floors does each riser module cover.

    Can the design incorporate prefabricated modular M&E systems of the floor services.

    And lastly and most importantly, just how are you going to get the plant, equipment and tradesmen to the relevant floor efficiently.
  3. 0
    Samer Zawaydeh ·
    Hi,

    I think that we did a couple of examples a while ago:

    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=1&Top=70998&page=2

    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=1&Top=67703

    With kind regards,

    Samer
  4. 0
    Mike Testro ·
    Hi Samer

    I often forget what I have done before - I am getting to the age where I consider the hereafter.

    I climb to the top of the stairs and then think "What am I here after"

    And another thing when I bend down to pick something up I ask myself "Is there anything else I can do while I am down here?"

    Best regards

    Mike Testro.
  5. 0
    Samer Zawaydeh ·
    Dear Mike,

    Your doing excersises. We only get better with practice.
    It seems that the Construction guys are hiring planners and they assume that the planners will do the Schedules without any communication with them.

    I was going to start a few pages to reply, then I remembered that we did a discussion for a hotel and we were talking about the risers.

    Our friend should do a search on PP for what he wants and he will find plent of information.

    With kind regards,

    Samer
    PS I am eager to find out what his reply is going to be.