Skip to content

Modifications in the updated Program from Base plan

Shaji MohamedMember for 17 years 5 months
Created
2
2
0
Hi.,

I have one Base plan with some logics between activities.After 3 months of update, i felt that the sequence (not only sequence,some of them) considered in the Base plan is having some issues or you can say that those can be considered in some other way. Please give me some suggestions to change the sequences or durations in the Updated program from Base plan. Is it the right thing to do or not.

Regards.,
S. Shaji Mohamed

2 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Shaji,

    Of course it is the right thing to do. It depends on the size of your project and the complexity of it. If you have a Contract and you submitted a Program of Works and the Engineer didn’t return with comments, then this is the Schedule that you (Contractor) will be following to complete the project.

    I assume that you are using FIDIC, and following article (8/3) once you realize that the actual progress at site does not represent the Program of Works, you need to modify your Program of Works to represent the actual (new information), making sure that you abide by the Conditions of Contract (scope, time).

    With kind regards,

    Samer
  2. 0
    Shah. HB ·
    Hi Shaji

    In the existing baseline [ without updates ],you can revise the network logic where you find the issues and than update it with actual site scenario and check the status.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?