Modifications in the updated Program from Base plan
In the Open Standard
Shaji MohamedMember for 17 years 5 months
- Created
- 2
- 2
0
Hi.,
I have one Base plan with some logics between activities.After 3 months of update, i felt that the sequence (not only sequence,some of them) considered in the Base plan is having some issues or you can say that those can be considered in some other way. Please give me some suggestions to change the sequences or durations in the Updated program from Base plan. Is it the right thing to do or not.
Regards.,
S. Shaji Mohamed
I have one Base plan with some logics between activities.After 3 months of update, i felt that the sequence (not only sequence,some of them) considered in the Base plan is having some issues or you can say that those can be considered in some other way. Please give me some suggestions to change the sequences or durations in the Updated program from Base plan. Is it the right thing to do or not.
Regards.,
S. Shaji Mohamed
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?