Design Drawings Issue
In the Open Standard
Tasnim YusoffMember for 16 years 3 months
- Created
- 4
- 2
0
Hi,
I have question regarding extension of time. How to justify how many days the contarctor entittle for EOT.
Example : We have 100 days for design submission. In between we submit 3 batch of drawings. 1st batch came back and got comment from the client and need to do resubmission. After few re-submission the client approved the 1st batch drawings. How to justify if the contractor entittle for any delays cause by this process?
In between contarctor submit 2nr and 3rd batch drawings.
Thank you
I have question regarding extension of time. How to justify how many days the contarctor entittle for EOT.
Example : We have 100 days for design submission. In between we submit 3 batch of drawings. 1st batch came back and got comment from the client and need to do resubmission. After few re-submission the client approved the 1st batch drawings. How to justify if the contractor entittle for any delays cause by this process?
In between contarctor submit 2nr and 3rd batch drawings.
Thank you
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?