4 resources for a Activity
In the Open Standard
Shazia khanMember for 18 years 5 months
- Created
- 20
- 6
0
Good Monig. Mr Rodel
I have an activity 10 days duration max.working Hr 10/d
This activity having four resources 2 nonlabour and 2 labour,
activity name is Foundation, OD 10 days. ( cal 6D/week)
Resource , 1 Execavator Nonlabour.
2. Execavator Operator (labour)
3. Roller Operator (labour)
4. Roller (nonlabour)
first 5 days for excavation, and last five days for Rolling,
i assing 100 units per resourece to avtivity all resource are over alocating,
Means in Res Sparesheet shows 12hr/d and Execavator working 14 Hr/d for 2 days.
Please advise me how i can assign these resource to activity avoid the resource over allocating.
How many units i have to allot for each resource so Res must work 10 hr/d only and work muct finished with in 10 days,
Thanks & Regards
I have an activity 10 days duration max.working Hr 10/d
This activity having four resources 2 nonlabour and 2 labour,
activity name is Foundation, OD 10 days. ( cal 6D/week)
Resource , 1 Execavator Nonlabour.
2. Execavator Operator (labour)
3. Roller Operator (labour)
4. Roller (nonlabour)
first 5 days for excavation, and last five days for Rolling,
i assing 100 units per resourece to avtivity all resource are over alocating,
Means in Res Sparesheet shows 12hr/d and Execavator working 14 Hr/d for 2 days.
Please advise me how i can assign these resource to activity avoid the resource over allocating.
How many units i have to allot for each resource so Res must work 10 hr/d only and work muct finished with in 10 days,
Thanks & Regards
20 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
