Max time/unit for Proecuement Activitiy
In the Open Standard
Shazia khanMember for 18 years 5 months
- Created
- 1
- 4
0
Dear Sir ,
I have Procurement Activity od is 15 days and cal.5d/week
i have assign a resource ,( Procurement Engr.) he will work only for 2 hr/d for 15 days,
in Resource tab Bugeted Unit is showing 24 while it should be 30
Max time/unit * od 2 * 15 = 30 Hr.
Could you please advise where i am wrong.
Thanks
I have Procurement Activity od is 15 days and cal.5d/week
i have assign a resource ,( Procurement Engr.) he will work only for 2 hr/d for 15 days,
in Resource tab Bugeted Unit is showing 24 while it should be 30
Max time/unit * od 2 * 15 = 30 Hr.
Could you please advise where i am wrong.
Thanks
1 reply
Oldest firstLog in or join to reply