Sub-Contractor. WBS

Shazia khanMember for 18 years 5 months
Created
3
5
0
Dear Sir

Could you please advise I have sub-contractor for my project.

This Sub-Contractor where will be cover under , Procurement WBS or a separate WBS for them in a EPC Project.

Example,

1.ENGG.
1.SUBCONTRACTOR
1.PROCUREMENT
1.1 SUBCONTRACTOR

1.CONSTRUCTION

1.COMMOSSIONING

Thanks & Regards

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Shazia,
    You have 2 ways of dealing with this scenario. Either creates a WBS for subcontractor or inserts a WBS for contractor for each main WBS and create a Activity Code to identify Subcontractor when filtering, Group & Sort.
  2. 0
    Gary Whitehead ·
    I would have procuring of the subcontractor under procurement wbs, and the work they are doing for you (engineering, construction or commissioning) under that wbs

    It largely depends on what you use your wbs for though.

    As rodel says, you can use activity codes to identify subby work
  3. 0
    Shazia khan ·
    Thanks for your reply.