Skip to content

Sir Mr.Rodel

Shazia khanMember for 18 years 5 months
Created
4
3
0

Please , to inform you that i ahve sent a schedule by email to you

this Shc. related to Activity Finshed Time ,

Thanks and Best Regards

4 replies

Oldest first
  1. 0
    Shazia khan ·
    Dear Mr.Rodel

    I wish to inform you that i have fix the problem

    I had change duration as well as relationsip.

    now all activity has right start and finished time.


    Best Regards
  2. 0
    Rodel Marasigan ·
    Shazia,
    Good Work! As I noticed on your schedule, the source of the problem is from changing calendar from 10hrs to 8 hrs which resulted to decimal places (i.e. 1d = 1.25d). Even you corrected the durations but relationship lag still have decimals that need to be correct. That should fix the problem.

    Best Regards,
    Rodel
  3. 0
    Shazia khan ·
    Dear Sir

    Thanks for your reply.

    the total Duration still 254.8 days.

    Could you please provide Steps by steps how to solve this problem.

    how to fix relation lag decimal.

    I can make it round figger

    2. i have finished Milestone , i want close all activity ends , other then start and end activity,

    this mile stone still leave with out Succ, because these are Finished MS

    Best Regards
  4. 0
    Rodel Marasigan ·
    Shazia,
    Total duration is based on Global Default Calendar. You need to change the Global Default Calendar and use 6 days calendar that you used and also under that calendar settings change the Time Period to match the calendar. (i.e. 10/d, 60/w...etc...)

    For relationship lag decimals you have to change it manually. Make sure it match the calendar that activity use (i.e. for activity using 5 days 8h/d and activity using 6 days 10h/d)

    Best Regards,
    Rodel

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?