Hi Experts

Could you please . share your exprience.

Finish Mile stone Must have Pred.. & Sucss. or it let witout sucss.

Thanks

5 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Shazia,
    At least have predecessors if last activity and should have both if in the middle of the program unless for special purpose.
  2. 0
    Shazia khan ·
    Sir

    If i will if it is open then any effect on resource loading.

    Thanks
  3. 0
    Rodel Marasigan ·
    Shazia,
    No but it will show a big float if in the middle of the program.
  4. 0
    Shazia khan ·
    Dear Sir

    Could you please advise me .

    Material cost like Hvac. elevator, concrete , exterior & enterior .

    where i can set in Material cost or i ca consider as expanses.

    my resource is cost calculate from unit/time bases.

    i have rate for resource per/hr.



    Please advise
  5. 0
    Rodel Marasigan ·
    Shazia,
    That’s all material cost. Samples of Expenses are Travels, Car rentals, Office Supplies, Consultants, etc.. and other one time cost that belongs to the Projects.

Log in or join to reply