Trend

Shazia khanMember for 18 years 5 months
Created
4
5
0
Hi-experts,


How to define in term of Trend,

How it will work for Projects,

Best Regards

4 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Shazia

    A trend is a projected future end derived from a set of known data.

    It will be theoretical and the statistical risks have to be clearly understood before making any use of a trend for any purpose.

    Best regards

    Mike Testro
  2. 0
    Shazia khan ·
    Dear sir ,

    Thanks for your reply,

    well, i want know that it is inbuilt in P6 or it is diffrent software


    I am using P6 ver 7

    Best Regards

  3. 0
    Mike Testro ·
    Hi Shazia

    The inbuilt histograms - for example Labour Resources - derive from known data that has been entered.

    This does not generate a Trend.

    If your project is getting behind then the projected completion date would be a Trend.

    Best regards

    Mike Testro
  4. 0
    Shazia khan ·
    Dear Sir.

    Thanks so much for explanation.

    It is very clear for me,

    Best Regards