Skip to content

Concrete Frame - Output Rates

Michael EnrightMember for 16 years 1 month
Created
1
2
0

Everyone have any information regarding the following concrete frame methods with regards to labour gangs / pour sizes / formwork erection output rates etc.

 

  • Flat slab
  • Ribbed slab
  • Waffle slab
  • Band and beam slab
  • Deep beam and slab
  • Hybrid
  • Pre-cast
  • Tunnel form

Thanks

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi Michael All production

    Hi Michael

    All production outputs should be extracted from the cost plan / boq.

    If the estimator has set down a labour - plant - material beakdown then total resource values can be extracted and converted to hours by way of the resource cost rate.

    If you do not have such a breakdown then you can apply a percentage that represents the labour value - applied to the net total - and again converted to hours.

    If you have any doubt about what percentage to use then consult the estimator or qs or refer to any of the pricing books.

    You should avoid using Ad Hoc production rates because this will have no bearing on your particular project.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?