Show time in minutes
In the Open Standard
Dante ManitoMember for 19 years 8 months
- Created
- 5
- 2
0
Dear All,
Recently, i made an schedule for the our project but i noticed that there an error in dates, it look like this.
Activity Duration Start Finish
Activity 1 1 2 September 2010 11:00 3 September 2010 11:00
I have check already the calendar and other settings but the same nothing change. Calendar setting was 7:00 AM to 17:00 PM. The correct date should be 2 September 2010 07:00 - 2 September 2010 17:00
Please help me solve this problem.
Thanks,
Dan
5 replies