Greetings Planners!

I need some information / advice about the capabilities of this "ATC" software.( http://www.interplansystems.com) I have zero exerience and have yet to find any other planners / schedulers with experience.  The number one issue that would be VERY helpful is in regards to exporting to Excel (CSV, Text, etc)....

A little background of what I'm tasked with starting in two days:  Move 1500 work plans (roughly 5000 activities) from ATC to P6. 

The importing,etc. portion isn't an issue once I have the raw data, but I was curious of the exporting capabilities of ATC.

ANY information would be GREATLY appreciated!

Cheers, Thanks, Regards, and G' Day!

Shane

1 reply

Oldest first
  1. 0
    Bernard Ertl ·

    Hi Shane,All ATC reports can

    Hi Shane,

    All ATC reports can be "printed" to Excel - exporting the data in a number of different formats.  Please send an email to InterPlan Systems' tech support and we will assist you.

    Cordially,

    Bernard

    InterPlan Systems