In P6: Can only one Resource Type (e.g., Labor and NOT Nonlabor) update the entire Units % complete?

Moe BarkoukyMember for 15 years 11 months
Created
1
2
0

Hi All,

 

I want the actual units of a certain (Labor) Type resource and not the actual units of the combination of resources allocated to the activities to update the UNITS % COMPLETE .  e.g.,  for a given task, i have two types of resources allocated to it, one of type LABOR and the other of the type NONLABOR..my question : can the UNITS % COMPLETE be only updated based on the quantities of the LABOR type only resource?

 

Thanks a bunch

 

Moe

1 reply

Oldest first
  1. 0
    Khaja Sharief ·

    P6 considers only labour &

    P6 considers only labour & non labour units for deriving units % complete and will not consider material units for calculating percentage complete.

    The calculation of Activity % Complete = Units % Complete = (Actual Labor Units + Actual Nonlabor Units) ¸ (Actual Labor Units + Actual Nonlabor Units +Remaining Labor Units + Remaining Nonlabor Units).

    If multiple resources have been assigned to the activity it would be sum of all labor and nonlabor units.