Standard labour productivity/manhours/mandays for various building activities

Swaminathan RamasamyMember for 15 years 11 months
Created
1
2
0

Does anyone have standard labour productivity/manhours/mandays for various activities in construction for Gulf region, excel sheets with datas or website from where I can get this info?

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi Swaminathan There is no

    Hi Swaminathan

    There is no such thing a standard outputs - every job is unique - therefore go to the BoQ / cost plan and extract the output rates from the prices.

    Best regards

    Mike Testro