Skip to content

MEP Clearance delay : Tower Project : Interior Sub Contractor

Hemanth KumarMember for 23 years 11 months
Created
4
6
0

MEP Clearance Delay  : Tower Project : Interior Subcontractor

 

during tender stage a sigle date MEP clearance was given for an entire floor ( A floor is having 30 Rooms \Areas)

Interior Sub Contratcor Submitted a plan based on floor clarance dates taking a certain amount of duration to finish a floor , say 100 days

Actually at site only a small  part /  clearance was given on the planned MEP clearance date

and after 100 days still several rooms in a floor not cleared for subcontractor

How effectievely this delay can be demonstarted in updated plan were there is no roomwise plan submitted ?

Thanks

Hemant

 

 

4 replies

Oldest first
  1. 0
    Michael Ramos ·

    Hi i think it will be

    Hi i think it will be difficult to defend if not room wise

    you will need to submit an excel file with room/area wise clearances

  2. 0
    Magdy Mic ·

    Hii  Hemanth,   I have the

    Hii  Hemanth,

     

    I have the same case of that, And the you should send a notice of delay for the MEP contractor or the main contractor, Demonstrate the impact of that delay showing the variance in dates for clearance , Then later on you can send Interim claim taking every delay case individually.

     

    Best Regards

    MAGDY

  3. 0
    Charina Matias ·

    I would suggest that you list

    I would suggest that you list down all the remaining rooms to be cleared. Make an adjustment in your updated plan for the clearances of each room. Take note that the adjustment can cause an additional variation order in the future.

  4. 0
    Hemanth Kumar ·

    Thanks for allI am planning

    Thanks for all

    I am planning to proceed like this

     I think the duration we have taken in the baseline is  considering a complete clearance at once

    if the area is not 100 % cleared , i will have to revise the Original duration based on % age of area cleared

    either weighted area or floor are %

    regards

    Hemant

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?