Copying Only Resources to all activities
In the Open Standard
Waheed MirzaMember for 15 years 10 months
- Created
- 4
- 4
0
Hi i had prepared a schedule with out assigning any resource to a project.now i need to assign as per project requirement.so i find little difficult to add resource to all activities.
my Question is can we add resources in one go to all activities and later we can change value if needed.sothing like that rather adding resource by clicking each activity and assigning.
hope you got the question
my email id: waheedmirza1@gmail.com
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?