Copying Only Resources to all activities

Waheed MirzaMember for 15 years 10 months
Created
4
4
0

Hi i had prepared a schedule with out assigning any resource to a project.now i need to assign as per project requirement.so i find little difficult to add resource to all activities.

my Question is can we add resources in one go to all activities  and later we can change value if needed.sothing like that rather adding resource by clicking each activity and assigning.

hope you got the question 

my email id: waheedmirza1@gmail.com

4 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    Waheed, please specify the

    Waheed,

    please specify the software that you use.

    It is easy in Spider Project but I expect that you use something else.

    Best Regards,

    Vladimir

  2. 0
    Kannan CP ·

    Hi Waheed, If you are using

    Hi Waheed,

    If you are using P6, then select the required activities in the schedule. After that right click the mouse and assign resource of your choice to the activities. It is the solution. In P3 go for a global change.

    Kannan

  3. 0
    Waheed Mirza ·

    thanks Kannan for wonderfull

    thanks Kannan for wonderfull reply

  4. 0
    Waheed Mirza ·

    Dear Vladimir Liberzoni use

    Dear Vladimir Liberzon

    i use Primevera 6.0 version...