Long shift in constructions work

Jehad Aldaoud PMP, PMI-SPMember for 16 years
Created
3
3
0

Good Morning to all planners 

 

as you know about long shift in construction work, there is many disadvantage in long shift in Long-term, please if any one have good reference to submit to project manager, 

 

I will be thankful 

best regards 

jihad aldaoud 

3 replies

Oldest first
  1. 0
    Puneet Gupta ·

    Jiahd:Reference paper is

    Jiahd:

    Reference paper is available on AACEI's website - "Predecting Productivity" by James M Neil and Lee E Knack.

    As per the author, working in longer shifts reduces the overall productivity. An adjustment factor of 0.1 is required if working on 7 days / 8 Hours or 6 days / 9 hours or 5 days / 10 hours.

    I hope this could help you.

    Best Regards

    Puneet Gupta

    Bau Management + Consulting GmbH

  2. 0
    Rockzy Sales ·

    Hi, thanks for sharing a good

    Hi,

     

    thanks for sharing a good inofrmation.

     

    Hmmmnn "working in longer shifts reduces the overall productivity" by a factor of 0.1?...that's interesting...

     

    I think there's a whole "project" to consider to before I could come up with the 0.1 factor..or whether longer shifts "really" reduces or increases productivity..... ;-)

     

    regards,

    the Rock

  3. 0
    Andrew Flowerdew ·

    AACEI article Cost

    AACEI article Cost Engineering Vol 46 No 4 April 2004: Impact of Overtime on Construction Labor Productivity

    is a good place to start if you can find a copy.