3D WBS
In the Open Standard
Jean-Yves MoineMember for 17 years 9 months
- Created
- 4
- 2
0
Dear all,
I would like to talk about a method I developed about Work Breakdown Structure: the 3D WBS.
The idea is that there are 3 dimensions by project phase.
- Engineering Task = Discipline x Functional Systems x Activity or (Discipline x SBS x ABS)
- Procurement Task = Localisation x Product x Activity or (GBS x PBS x ABS)
- Construction Task = Localisation x Product x Activity or (GBS x PBS x ABS)
- Commissioning Task = Discipline x Functional Systems x Activity or (Discipline x SBS x ABS)
There are 3D Cubes under each phase.
The list of tasks is obtained by matrix.
I think that all the projects have this standard WBS.
What do you think about this approach?
Regards,