Bridges help need

G TMember for 15 years 9 months
Created
1
7
0

Dear Forum,

Could u please urgently show me or advise location(web, URL) of some typical schedule for bridge construction, typical for 4-5 spans with piling, no water no river beneath... please I need urgently...

 

Thanks very much

Carlos

1 reply

Oldest first
  1. 0
    Daniel Limson ·

    You normally start

    You normally start with preparing a temporary traffic management or arrangement scheme (TTM or TTA) in the area for approval by the relevant Authorities.

    typical construction activities:

    1. Piling

    2. Pile Load Test

    3. Pile Trimming

    4. Pile Cap

    5. Cast Column

    6. Cast Column Head and Bearings

    Now it depends what kind of design you have (precast segments (post tension), precast T beams, Cast in Situ, etc.)

    7. Say we use precast T Beams lift in place

    7. Construct Bridge Deck, Drainage & Parapet

    8. Final wearing course and road markings

    The construction of the ramps can be done in parallel.

    Good luck!