Precommissioning / Commissioning Activities & Sequence

Angel CruzMember for 16 years 5 months
Created
7
4
0

Hi,

Actually I'm preparing draft schedule for Precommissioning & Commissioning schedule for LNG Terminal Project.

And I come out with these activities as follows:

 

Precommissioning:

  1. Hydrotest of Pipelines

  2. Leakage Test of Pipelines

  3. Flushing & Cleaning of Pipelines

  4. System dry-out

  5. Inerting

  6. Systematic Conformity Check of Equipment

  7. Static, De-energized Test of Equipment

Commissioning:

  1. Preliminary Check

  2. Functional Check

  3. Operational Test

  4. Pre-Startup activities

 

May I ask some advise to those who had the same experience on the questions below:

  Q1. Are the activities and sequence are correct?

  Q2. Is there any missing activity?

  Q2. Are these set of activities can be applied to both Utility System & Process System?

 

Thank you and Regards,

 

Angel

7 replies

Oldest first
  1. 0
    Maxime AUTHIER ·

    Hi Angel,   Here some element

    Hi Angel,

     

    Here some element of answers:

    - What you call "Preliminary checks" should be done during or before the Precom (I guess this includes the piping conformity check, instrumentation calibration, machinery alignment, Manhole closure ...)

    - For some systems you will not have all these activities (in particular inerting, dry-out for utilities as water ...)

    - For gas systems, flushing (with water) and dry out may be directly remplaced by Air blowing

    - For process system, you should identify the Safety valves calibration as this often is a critical activity

    - Some times could be identified for the closure of blocking points of the punch lists, depending on the way it works on your site 

     

    Hope it could help,

     

    Rgds,

     

    Maxime.

  2. 0
    Johannes Vandenberg ·

    Hi Angel Suggest the

    Hi Angel

    Suggest the following

    The items you show as precommissioning and commissioning are in fact part ot the construction, inspection and testing activities.

    The basic stream of the process of commisionning is as follows:

    • Complete all the construction, testing, and testing activities
    • Carry out the complete and all the Mecancally Completion activities.
    • Then make a precommisionng plan detailing all requirements of the "Systems"
    • These systems are detailed in the P&I D's. These can be process, utilities, firewater, safyty system, Powergeneration, power distibution. lichting & small power etc.
    • Further plan all recourses, vendor assistances, commisioning engineers, consumables an spare parts, labour for assistance
    • Establish safety and workpermit systems

    The next step is commisioning

    • After all the precommissioning activities are completed the commissioning can commence. Take that commissioning starts when the systems "are going live".
    • In many occasions the commissing start with the electrical en instrumentation systems, such as powergenerations and distribution.
    • Then the plantoperation systems shall be done. Etc.

    Trust that you answers some of your questions

     

    Regards Johannes

     

     

     

       

  3. 0
    Angel Cruz ·

    Thanks Johannes & Maxime for

    Thanks Johannes & Maxime for the replies.

  4. 0
    Syed Zaidi ·

    Can anyone provide me

    Can anyone provide me Primavera 6 version commissioning plan? in .xer format? plz email at kalbe00@hotmail.com

  5. 0
    Ash Allam ·

    Hi Guys, Would love a copy of

    Hi Guys,

     

    Would love a copy of the XER's to get as well.

    ash.allam@hotmail.com

     

    Thanks in advance.

    Ash

  6. 0
    Ash Allam ·

    Can you please sene me a copy

    Can you please sene me a copy of the XER's

     

    Ash.allam@hotmail.com

  7. 0
    Gary Whitehead ·

    No-one has offered to provide

    No-one has offered to provide XERs on this thread, and it is 3 years old.

     

    Thread locked.