Skip to content

P6 Update

Khadar BashaMember for 15 years 8 months
Created
0
4
0

Hi,

I am facing difficulty while updating the schedule

i am updating the progress in activty% column and same progress was appearing in the Unit % column too and that it is what my requirement too but in some activities it is not happening. when i schedule the program the Unit % column progress is coming back to zero(0).which shoud be same as activity % column.

if any body know the solution please let me know where and what is the error.

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?