Changing sequence of work in updated programme

Sinan FahmiMember for 19 years 10 months
Created
4
2
0

Dear Planners,

     while I am updating my programme of work I faced out of sequence activity, my question is that is it possible to change the relation ship of this activity because after scheduling the early finish of this activity is still be driven by its predecessor activity?

 

Thanks in advanced

4 replies

Oldest first
  1. 0
    Shah. HB ·

    Hi Sinan Fahmi, PSPYou can

    Hi Sinan Fahmi, PSP

    You can revise the relationships if it sounds illogical before updating the program and it has to be recorded for substantiation

    Regards

    Shahul

  2. 0
    Jose Frade ·

    Hi Sinan   Quite often

    Hi Sinan

     

    Quite often relation of activities have to be changed (most common reason is to reflect a possible change on project management strategie or mitigate some unexpected impact from late completion of activities, etc).

    In every case, relation has to be changed and event noted for later reference. Schedule has to be recalculated every time it happens.

     

    BR

    JMFrade

  3. 0
    Sinan Fahmi ·

    Thanks alot..... its clear

    Thanks alot..... its clear for me now

  4. 0
    Hadi k. Shabibi ·

    Your can change it if you

    Your can change it if you find the change is necessary during updates, but should be noted and recorded,

    list the change in a LOG file and write the reason of the change then send it to client/PM for his record.