Can we create relationship in Resouces

Kumar BaijuMember for 15 years 8 months
Created
1
4
0

Hi to all

Can we give the relation for different resources for any activity as we do in activity.
for example if we assign two different resources 1. Engineer and 2nd Draftmen. can we give the relation so that Draftmen will start work after Engineer work finish.Please guide me

Thanks for support in advance
KBJ

1 reply

Oldest first
  1. 0
    Gary Whitehead ·

    Primavera can't do that, nor

    Primavera can't do that, nor can MS Project. Spider may, and I'm not sure about Asta.

    But why don't you just have a seperate activity per resource?

     

    Also, please don't post the same question in multiple forums. I have deleted the copies.

     

    Cheers,

     

    G

Log in or join to reply