defects of weight by cost

Ji WeiMember for 16 years 5 months
Created
2
3
0

When we use cost as the standard of split weight in progress control, we found that some work in construction stage spend several days, but it take big part in weight because of cost. When the material procured, we take some actural percentage in progress. But I think it is still difficult to correctly present the progress of construction works.

Anyone knows how to make it better for progress control when we use cost as the weight?

I hope you can share your experience in progress control with me.

Thanks! 

2 replies

Oldest first
  1. 0
    Vishnu Gupta ·

    HI.. ANYONE CAN GIVE DETAILS

    HI..

    ANYONE CAN GIVE DETAILS HOW TO FABRICATE REDUCER FROM PIPE AND HOW TO CALCULATE INCH DIA FOR BILLING PURPOSE

  2. 0
    Anoon Iimos ·

    what kind of pipe?; inch-dia

    what kind of pipe?; inch-dia is number of joint multiplied by diameter of pipe in inch.

    @ ji wei, use productivity (man-hours and/or equipment-hours) and backed-up by volumetric calculations (or quantities).