Early and Late Dates

Darwin GracianoMember for 15 years 4 months
Created
3
2
0

Hi All,

Recently I've created 3rd revised baseline programme for our company.  But when I assign our new baseline programme, I've noticed that some of the lates dates are earlier than the early dates.  Is it really possible to happen?

Thanks & Regards,

Darwin

3 replies

Oldest first
  1. 0
    Daniel Limson ·

    Darwin, You need to check

    Darwin,

    You need to check further and investigate a little bit more. Late Dates are supposed to be the latest dates you can delay an activity without delaying some key dates and/or the overall completion date. In other words, previously you had floats on these activities, now you are saying that 'Late Dates' are earlier than the 'Early Dates', the only logical explanation to this anomalies is that you now have a negative float on some of these activities that is why you have this case. Check 'total float', if you have negative floats then late dates will be earlier than the early dates

    Best regards,

    Daniel

  2. 0
    Darwin Graciano ·

    You're right Mr. Daniel. Some

    You're right Mr. Daniel. Some of my total floats are negative already. I check out some links and construction procedures to be able to lessen all the negative floats. Thanks a lot.

    Best regards,

    Darwin

  3. 0
    Mike Testro ·

    Hi Darwin Negative float is

    Hi Darwin

    Negative float is usually caused by a Must End On constraint.

    Best regards

    Mike Testro

Log in or join to reply