Types of schedules

John PowerMember for 16 years 7 months
Created
1
2

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi John Basically the

    Hi John

    Basically the evolution of a construction programme goes something like this:

    1.  Tender Programme - should be at level 4 but rarely is.

    2.  Contract Programme - A development of the Tender programme - after award - based on the best information available - must be at level 4 - Sometimes called the Baseline Programme - submitted for approval

    3.  Revised Programme - Prepared when there are any changes in the scope of work or any delay events - the baseline saved in a new file name - often results in an EoT situation.

    4.  If the Revised Programme is approved it then becomes the new Baseline - numbered sequentially 01 > 02 etc.

    5.  A Mitigation programme is where the original logic in a revised programme is changed to reduce the end date at no extra cost to the contractor.

    6.  An Acceleration programme is where the overall duration is reduced with extra cost - this is very difficult to get right and should only be done after mitigation.

    Best regards

    Mike Testro