Critical Activities

Mohd AnjumMember for 15 years 8 months
Created
8
2
0

Hi ,

Quest: What is critical activity?When we get the activites critical? and how can we remove/tackle it?

Ans: I have several answers but got confused.

As a planner asking this small question is really a silly, but i need to clear my confusion.

so i will be glad if anyone could help me in simple language without any further confusion.

8 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    Activity is critical if its

    Activity is critical if its delay will delay project finish.

  2. 0
    Stephen Devaux ·

    Trouble is, sometimes an

    Trouble is, sometimes an activity's start may be critical but not its finish.  If A is a 15D activity and a SS+5 predecesor of B (on the CP), then a delay in the first 5 days of A will delay the project completion, but a delay in the final 10D of A won't (if it has Super Float). 

    Fraternally in project management,

    Steve the Bajan

  3. 0
    Mohd Anjum ·

    Frndz, I still didn't got

    Frndz,

     

    I still didn't got what i want,

    can anyone help me in detail.

  4. 0
    Vladimir Liberzon ·

    Hi Mohd, what details do you

    Hi Mohd,

    what details do you need?

    Activity is critical if it has no time reserves for its execution. Delay of critical activity execution delays project finish or major milestones where Finish No Later Than is defined.

    Any PM software finds critical activities when resources are unlimited. These activities have zero (or negative) total floats (Late and Early dates are equal or Late dates are earlier than Early dates). 

    When resources are limited finding critical activities is much more complicated and most PM packages produce wrong results (calculate wrong total floats).

  5. 0
    Shah. HB ·

    Hi The longest time path

    Hi

     

    The longest time path through the task network.
  6. 0
    Aijaz Syed ·

    Steve : Did u mean to say

    Steve : Did u mean to say that Delay time is the critical time ( critical path) , which extends the duration of project

     

    Aijaz

  7. 0
    Stephen Devaux ·

    Hi, Aijaz.I'm not quite sure

    Hi, Aijaz.

    I'm not quite sure of your question, so let me answer it this way:

    • Every project ALWAYS has a critical path (at least one!) of activity durations, constraints, and handoffs and other delays, which is the longest path.  This path determines the length of the project. Delays on this path make the project longer, while (and this is important!) reductions in time on this path will make the project shorter UNTIL another path becomes the longest path.
    • The respective activity durations, constraints, and handoffs and other delays on the critical path are each contributing various amounts of delay (depending on their durations, dependencies and location in the network) to the total duration of the critical path. This amount of time is each activity's critical path drag.

    For a (MUCH!) fuller discussion with Miklos and Rafael, see the Critical Path Quiz discussion.

    Fraternally in project management,

    Steve the Bajan

  8. 0
    Stewart Green ·

    Hi Mohd A critical activity

    Hi Mohd

    A critical activity is any activity that (if delayed) will delay the overall project duration.

    The string of critical activities (that join up through the project) is called the "critical path", and the total durations on this path defines the overall duation of the project

    Activities that are NOT critical have "Float" (ie they can be delayed to a certain extent without delaying the overall project duration)

    A critical activity might be taken off the critical path by making it shorter in duration by (eg) allocating more manpower, or using a faster work-method. BUT, if successful with this, the critical path will simply move to another path (or string) of activities.

    There will always be a critical path somewhere !!

    Kind Regards

    Stewart