P6.V7 Software Bug Found... causing PMDB corrupted!!!
- Created
- 2
- 1
Hello Planning Folks,
Yesterday I found a dangerous bug in P6.V7 about the experiment of using filter by below condition
BL Project Total Float < 0
Then clicked OK, the Error Popup Message is shown event code AVAA0-0633-5, then I clicked "Exit" then P6 Application was self-closed and I cannot open P6 again.. I have to re-install the software and my SQL Database cannot be recovered. So I just realize as well that this case is not facing problem when applied to P6.V8.
Be Careful! about this sensitive bug that might harm your database especially to whom handling & collecting with huge project data.
Good Luck for All !!
Praves Suppa