Earned value on completed activities
- Created
- 3
- 1
Hi,
Im looking at conducting earned value without any sort of formal company proceedure and i thought i would get your opinions?
We have some activities in our schedule that will be actualised even though the work has not been fully completed. This is because it is a rail project and the possessions which have define starts and finishes have to end then (to hand the track back). However if all our expected work was not complete on time (and we will have to plan a future activity to complete) automatically primavera marks activity (physical or duration) as 100% complete.
Hows the best way to do earned value on this, because even if actual units/costs are less then the software will think at 100% complete that we have come in under budget?
Any ideas?