Finish Milestone
In the Open Standard
AB TimoMember for 15 years 3 months
- Created
- 5
- 2
0
Hello All,
I have Planned a Project and after Finalizing the Schedule I've just Noticed that the Finish milestone is Note Giving the Required Date.My Project will Be Handed Over On 15th Dec,2012 and I gave FF RElationship to Finish milestone and last activity of the Project (Site Clearance-->FF-->Finish Milestone),But Instead of Showing 15, Dec 2012 as the Complition Date, the Finish Milestone is taking One day more i.e, 16th Dec 2012.I have not given any lag and have asigned FF Relationship also.Can anyone tell me the reason??
Regards,
Faiz
5 replies