Planned Vs Actual
In the Open Standard
AB TimoMember for 15 years 3 months
- Created
- 8
- 4
0
Hello All,
if you have Planned a project and after starting updating it,you find that you have entered a couple of activities that are not happening actually and Need to be deleted.What do you do??
Will you have to make another schedule?? Because if you delete those extra activities then your baseline will be disturbed and it will ultimately disturb the Logic.
Please give you opinion.
Best Regards,
Faiz