Resource Overallocation.
- Created
- 4
- 3
Hi Guys,
I added a resource "Tile Fixer" to an activity using following steps.
1 .In Resource window added Resource "tile Fixer.Assigned it calender (8hrz/Day),entered Price/Unit.
2 .In activity window click on Resource "Tab",selected the Resource "Tile Fixer" and Entered "16h/Day" in "Remaining Units" Column (Because 2 Tile Fixers were required to work each day for 8 Hrz).
After That when I see the "Resource Usage Profile" window it is showing "Overallocation" of 8 Hrz each day.Please tell me that is it correct to enter 16h/Day or i should enter 8Hrz/ Day two times???
Best Regards,
4 replies
Oldest firstLog in or join to reply