Activity usage spreadsheet issue

AB TimoMember for 15 years 3 months
Created
1
2
0

Hi all P6 Users.

White using activity  usaege spreadsheet  tab to calculate the monthly accumulative PV and Ev, I have encountered the following Problem.I hope someone can suggest the solution.

Activity spreadsheet window- --> right click ---> spreadsheet option ----> "calculate average" --->here i have to enter 1853469.89 (cost is 185346989 Sr / 100 = 1853469.89) , but it is not taking complete value i,e not taking more than 6 digits number). can you check this option and solve the issue????

 

Regards,

1 reply

Oldest first
  1. 0
    Aries Arian ·

    Hi Faiz,Why do't you export

    Hi Faiz,

    Why do't you export your values from spredsheet in "excel",and work there.

    Regards,

     

    Aries