Hi all P6 Users,

Can any one Explain me that how P6 Calculates Origional Duration and Actual Duration.I was applying a Threshold "Duration % Of rigional (%)" and you must know that

 

Duration % of Origional (% )=  Actual Duration / Original Duration * 100

Now I Am not having a clear understanding that how P6 Calculates Actual Duration and Origional Duration Values.

Please Clear This Concept.

Thanks in Advance.

Arian

3 replies

Oldest first
  1. 0
    Aries Arian ·

    Please Give Response.

    Please Give Response.

  2. 0
    Shah. HB ·

    Hi Aries Arian  Check this

  3. 0
    Amit Parmar (PMP) ·

    Hi Aries,Can you tell me if

    Hi Aries,

    Can you tell me if you want formuale for Duration % Complete? Cause Original duration is a punched in value and Actual Duration is etiher punched in or Calculated depending on whether you entererd Remaining Duration or Actual % Complete.

    Regards

    Amit

    Check out my blog on Primavera at http://www.primaverablog.in

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?