Program for Mosque
- Created
- 2
- 4
2 replies
Oldest first- 0MMMohammad Mojahid Akhtar ·
Dear Plz find activities
Dear Plz find activities for Mosque
Activity ID Activity Name
Mosque ( B - 040 ) (Z7)
Mosque ( 7-B040-1 )
Site Work
Z7B040-1-0010 Excavate for raft foundation
Z7B040-1-0020 Drill Probe hole
Z7B040-1-0030 Grout Probe hole
Z7B040-1-0040 50 mm thick blinding concrete raft foundation
Z7B040-1-0050 Raft foundation
Z7B040-1-0060 Bituminous coating raft foundation
Z7B040-1-0080 250mm granular fill under ground slab
Z7B040-1-0070 Backfill around raft foundation
Concrete
Z7B040-1-0140 Minaret Construction up to Slab level
Z7B040-1-0090 Concrete blinding under grd slab
Z7B040-1-0100 Concrete trench for under slab services
Z7B040-1-0110 200 mm thk ground floor slab
Z7B040-1-0440 Fabrication of P P ( Priority 2 - 40,244,50,265,291,90,60,,61)
Z7B040-1-0120 Install P.C.C.Columns
Z7B040-1-0130 Install P.C.C.Beams
Z7B040-1-0210 Form / Pour Staircase
Z7B040-1-0150 Erect / Fix Precast Concrete Panel
Z7B040-1-0160 Erect / Fix Precast Minaret Panel
Z7B040-1-0180 Installation of Roof Hollow core slab
Z7B040-1-0190 Erect / Fix Mehrab Panel
Z7B040-1-0200 Install Parapet
Z7B040-1-0220 Roof screeding
Z7B040-1-0230 Plinth Protection Slab
Masonry
Z7B040-1-0240 Blockworks
Metal
Z7B040-1-0250 PVC grating trench cover
Z7B040-1-0260 Installation of handrailing
Z7B040-1-0270 Installation of Brass plate Hilal
Wood & Plastic
Z7B040-1-0280 Compact kitchen Unit
Thermal & Moisture Protection
Z7B040-1-0290 Roof water proofing
Z7B040-1-0300 Toilet & bathroom waterproofing
Z7B040-1-0310 Finish Expansion Joint
Door & Windows
Z7B040-1-0320 Install Steel Frame & Door Panels
Z7B040-1-0330 Install Aluminum Windows
Z7B040-1-0340 Install Ironmongery ( Hardware )
Z7B040-1-0350 Install Roof Hatch
Z7B040-1-0360 Install Fabric Curtains
Finishes
Z7B040-1-0370 Plastering of Walls
Z7B040-1-0380 Plastering Ceiling
Z7B040-1-0410 Internal painting preliminary coats
Z7B040-1-0420 Floor terrazzo tiles & skirting
Z7B040-1-0480 Install Aluminum strip Suspended ceiling
Z7B040-1-0390 Floor screeding for carpet
Z7B040-1-0400 Trowelled concrete w/ hardener
Z7B040-1-0430 Floor terrazzo tiles - External
Z7B040-1-0460 Glazed ceramic wall tiles & skirting
Z7B040-1-0474 Mosaic Tiles Mehrab
Z7B040-1-0450 Terrazzo treads & risers ( stair finish )
Z7B040-1-0490 Final coat of paint
Z7B040-1-0470 Unglazed ceramic floor tiles
Z7B040-1-0476 Mosaic Tiles Toilets
Z7B040-1-0500 Install Carpet
Specialties
Z7B040-1-0510 Install W.C Door
Z7B040-1-0520 Install Toilet & Bathroom accessories
Mechanical
Z7B040-1-0530 Install Soil & Vent pipe work
Z7B040-1-0540 Install Cold Water Pipework & Valves
Z7B040-1-0590 Install Duct work
Z7B040-1-0550 Install Hot Water Pipework & Valves
Z7B040-1-0600 Install volume Dampers
Z7B040-1-0560 Install Sundrise & Valve
Z7B040-1-0570 Install Electric water heater
Z7B040-1-0610 Install Fan coil unit
Z7B040-1-0620 Install Cooled Condensing unit
Z7B040-1-0630 Install Sand trap louvers
Z7B040-1-0640 Install Exhaust fan
Z7B040-1-0650 Install wall Air Conditioning unit
Z7B040-1-0580 Install Sanitary fittings
Z7B040-1-0660 Install Fire Protection equimpent
Electrical
Z7B040-1-0670 Install Conduiting & boxes
Z7B040-1-0680 Install Cabels and Wires
Z7B040-1-0690 Install/Terminate Wiring Devices & Disconnect Switches
Z7B040-1-0700 Install/Terminate Panelboards
Z7B040-1-0710 Install Lighting Fixtures
Z7B040-1-0720 Install Fire Alarm System
Z7B040-1-0750 Install Grounding System
Z7B040-1-0730 Install Public Address System
Z7B040-1-0740 Install Telephone System
Z7B040-1-0760 Install Lightning Protection System