Skip to content

Financial Periods

AB TimoMember for 15 years 3 months
Created
7
4
0

Hi All Primavera Users,

 

I have created financial perioods for a Project "Project A" but when I created another project separately "project b" and tried to creat Financial periods for it,I have found that the Financial Periods for "Project A" are already present there.I did not find any option of "show current project financial periods" or something like that.can any one explain that how we can add separate financial periods to different projects without getting interrupted by other projects data.

 

Regards,

7 replies

Oldest first
  1. 0
    Greg Horsfall ·

    The financial periods

    The financial periods themselves, are created once for all projects. The data for each period is held per project and is not mixed.

  2. 0
    Greg Horsfall ·

    The financial periods

    The financial periods themselves, are created once for all projects. The data for each period is held per project and is not mixed.

  3. 0
    Rafael Davila ·

    In other words financial

    In other words financial periods in P6 are global while financial periods in P3 are project specific. Both are poor implementation of past period performance record keeping and math. 

  4. 0
    AB Timo ·

    Hi Rafael & Greg,You mean its

    Hi Rafael & Greg,

    You mean its better not to use this feature???

    If Finacial Period for one project is starting from 01-11-2011  and  Ends at 07-011-2011  & for another project it is starting from 03-11-2011 and ends at 10-11-2011,then how to creat  it..As far as I have seen it gives an error that the dates are within the Previous financial period.If iy can not give us the exact dates for every project then what is use of it???

    Please clarify.

     

    Thanks

  5. 0
    Rafael Davila ·

    Depending on the software you

    Depending on the software you might need to use financial periods.

    What I am saying that as per P3 they must be pre-defined by job, in P6 globally. That in these software to get the correct distribution for past performance you must update strictly as per financial periods and then post the update every time and your reports will be limited to a single pre-defined period to get correct past performance distribution, otherwise why so much fuss about it. With these software you will be able to generate past performance reports but only when using a report period equal to the pre-defined the distribution will be correct.

    In other software you can get reports for any financial period [can be any, not merely a few hundreds different financial periods; every 2 hours, every day, every month] defined after you update your job in any combination of period updates. The following report is for a period of 2 hours, you can see the correct past performance for 2 hour detail. I updated the job using a weekly update but one activity was reported working only 2 hours a specific day and it shows correctly, is simple math other software can do. Look at November 8, activity one worked only 2 hours that day and reported some cost during these two hours [8:00 to 10:00 am $300].

    Past performance is not only about the distribution of costs per past periods but also about the actual production per period, necessary to show changes in productivity on a claim. Some software are not good at keeping detailed records for past performance and their reporting is limited.

    Photobucket

    I wonder about Asta PP because on their literature I saw an excellent example of detailed activity updating and reporting.

    Photobucket
  6. 0
    Rafael Davila ·

    Suggest creating separate

    Suggest creating separate databases to overcome P6 limitation, preferably other than the basic Oracle Database that might limit you to a single database per installation and that might freeze if you go over its limit.

    About how to create several "financial periods" for a single project that might be too much for P6.

  7. 0
    AB Timo ·

    Rafael,Thank You.i Really

    Rafael,

    Thank You.i Really Appriciate your participation here at PP.

     

    Best REgards.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?