EVA terminology - useful info

Tom FullerMember for 15 years 3 months
Created
2
4
0

Hi guys - See below, which might assist in understanding EVA terminology.

  

TERMINOLOGY

VALUE

DESCRIPTION

SOURCE OF INFORMATION

Budget at Completion (BAC)

Contract budget

The total budget for each activity

Contract schedule

Earned Value (EV)

Contract budget x actual % complete

What we’ve actually earned for work performed to date

Contract schedule, daily reports

Planned Value (PV)

Contract budget x planned % complete

What we planned to earn to date

Contract schedule, tender

Schedule Performance Index (SPI)

Earned value / planned value

Compares what we’ve actually earned to date with what we planned to earn to date

Contract schedule, daily reports, tender

Schedule Variance (SV)

Earned value – planned value

Difference between planned profit/loss to date and actual profit/loss to date

Contract schedule, daily reports, tender

Cost Performance Index (CPI)

Earned value / actual cost

Compares what we’ve actually earned to date with what we’ve actually spent to date

Contract schedule, daily reports, IPM cost reports

Cost Variance (CV)

Earned value – actual cost

Profit or loss to date

Contract schedule, daily reports, IPM cost reports

Estimate at Completion (EAC)

BAC / CPI

Estimated total cost to complete the activity

Contract schedule, daily reports, IPM cost reports

Estimate to Complete (ETC)

EAC – actual cost

Estimated total cost to complete the activity

Contract schedule, daily reports, IPM cost reports

Value at Completion (VAC)

BAC – EAC

Estimated profit/loss for activity

Contract schedule, daily reports, IPM cost reports

To Complete Performance Index (TCPI)

(BAC – EV) / (BAC – AC)

Similar to CPI. This is an indicator of “slack” or “negative slack” until the end of the activity

Contract schedule, daily reports, IPM cost reports

2 replies

Oldest first
  1. 0
    Rafael Davila ·

    Beware, SPI can be

  2. 0
    Stephen Devaux ·

    Tom,You might want to

    Tom,

    You might want to add:

     

    Critical ratio EAC (SPI X CPI)

    Cost EAC = BAC / (SPI X CPI)

    If BAC = $1M, SPI = .90 and CPI = .80, CR  = (.90 X .80) = .72.

    Thus, Cost EAC = $1M / .72 = $1,388,889

     

    This formula takes into account that, if you are both over budget and behind schedule, you'll be overspending (indirect costs, LOEs etc.) for longer than planned.  There is much empirical data to show that this is the most accurate EV predictor of Cost EAC.

    Fraternally in project management,

    Steve the Bajan

     

Log in or join to reply