Inporting XER to Primavera Risk Analysis

Sm PumMember for 15 years
Created
2
20
0

Hello All Planners,

I have Imported an XER file to Primavera Risk analysis but it is not showing WBS Bands.Only activities are listed.Any Suggestion?

 

Regards

2 replies

Oldest first
  1. 0
    Srinivas Doguparthy ·

    i am having doubt in

    i am having doubt in calenders

    when i am giving daates to activities from 24-12-2011 to 08-01-2011

    the original duration should be 16 days but it is showing 30 days

     

    how to resolve this problem

     

    when i am exporting the project and saving

    again when i am importing this project in primavera project details are coming but i am not getting OBS and EPS

    how to get this

     

    how can i change the order of activities in p6.7

    a1000

    a1500

    a1250

    a1450

    i should make it in correct order how to do

     

     

    please help me in these issues it will be very much helpfull to me pls pls pls pls

  2. 0
    Mohd Syahrul ·

    SM PUM, I think you missed

     


    SM PUM, I think you missed to check the WBS option during the import. "Organize by WBS project structure".
     
    srinivas doguparthy, can you detailed your calendar setup?