%age on p6 is different
In the Open Standard
Kashif KhanMember for 14 years 11 months
- Created
- 3
- 1
0
Hi All,
Just a small query, i convereted the progress from p6 to excel sheet, computed the weightage w.r.t duration of each activity and multiplied it to the current progress percentage, when added, it has given me an overall %age, but this overall %age is very different from the what the primavera p6 is giving, means primavera is giving 42% where as my excel computation is giving me 20% progress overall. WHY IS IT SO? plz help me in telling where am i wrong ?
regards,
kk