Constraints in P6
In the Open Standard
Dave ScottMember for 14 years 10 months
- Created
- 0
- 2
0
I'm semi-new to P6.
I'm trying to hold a date in my schedule. In the bottom activity box I have the dates selected that I want to hold, but in the schedule the * does not appear. When I update the schedule, it changes all 100% completed dates to the data date. If I change the data date, it changes all 100% done activities to that data date.
Any input would be apreciated.
Dave
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?