why different values?

Kashif KhanMember for 14 years 11 months
Created
4
3
0

Dear Planners,

Plz refer to the picture, my query is, why the value of budgeted hours (in red circle) is different as we multiply the price/unit with budgeted units (showing 8 but actually its 7.5 hours per day calender), as it should be 104x7.5=780 rather than 777

 

Please answer.

regards,

kk

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Kashif Probaly because

    Hi Kashif

    Probaly because your work pattern is  less than 7.5 but the number has been rounded up in the display.

    Check the hours and minutes in your work pattern.

    Best regards

    Mike Testro

  2. 0
    Gary Whitehead ·

    I believe this value is

    I believe this value is calculated using the hrs/day factor in Admin preferences menu, not using the activity calendar

  3. 0
    Neal Walsh ·

    Kashif, It could be that your

    Kashif,

     

    It could be that your decimel settings need reviewing, as it is appears to be rounding up to the near 30mins, similar to what Mike said.

    Although by calculation, it comes out at 7.47115 hours!

    Other than that, Paul Tobin owes you 52 bucks (technically)   :o)

     

    Walshy

  4. 0
    Kashif Khan ·

    great tip. thnx

    great tip. thnx

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?