why different values?
In the Open Standard
Kashif KhanMember for 14 years 11 months
- Created
- 4
- 3
0
Dear Planners,
Plz refer to the picture, my query is, why the value of budgeted hours (in red circle) is different as we multiply the price/unit with budgeted units (showing 8 but actually its 7.5 hours per day calender), as it should be 104x7.5=780 rather than 777
Please answer.
regards,
kk