Assigning a Material Resource in P6

Sm PumMember for 14 years 11 months
Created
1
2
0

Hello All Planners.

Please have a look at following example;

I added a Material Resource Named "Crushed Aggregates" in my schedule.I have changed resource type to "Material" and adjusted the price per unit.No the unit of measure that i want to keep is "Cu.m".The issues that i am facing are,

1- I am not able to find an option to make my resourse loading a "spread loading" i.e, I want to tell primavera tha 1000 C.m of crush is required for a certain activity in 2 weeks.The only way i find is assigning price per unit and then if i assign this esource to the activity,then it multiplies the price per unit with the duration,that i do not want.

I want to give my resuorse a certain price and qty that should be spread on total duration of activity.

 

I hope my question is clear.Like in primavera Risk analysis there is option of "spread loading " and "point loading".

If not then how you assign material resource to your activities.please guide.

 

Thanks

1 reply

Oldest first
  1. 0
    Raymund de Laza ·

    Hi, Manually edit the Budget

    Hi,

    Manually edit the Budget Units on the assigned resource.

Log in or join to reply