Changing original project start date after most of the project activities are entered in SureTrak 3.0

Ken JohnstonMember for 14 years 7 months
Created
1
4
0

i have started a new project and the owner wants to change the start date for working day calculation. I want to movethe start date and the activies to an earlier date.

1 reply

Oldest first
  1. 0
    Daniel Limson ·

    Hi Ken,There is actually a

    Hi Ken,

    There is actually a way to do it, I am not using Suretrack anymore but I have had that situation before and I believed you need to change the Project Start Date as you open the file (click overview) and you also need to adjust the data date.

    Regards,
    Daniel