Repeated milestone/ activity
In the Open Standard
Kashif KhanMember for 14 years 11 months
- Created
- 2
- 2
0
Hey,
Anyone could help me how to incorporate the milestone or activity repeating only for 4 hours in a week on the same time and on the same day.?
Lets suppose if the project is of 10 weeks, and i have a project meeting of 2 hours on each monday, then how to incorporate it into the program under a single WBS?... shall i have to write meetins activity 10 times or there is any other solution?.
Pleas ehelp,
regards, KK
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?