Standard Work week w/ basic Holidays

Spencer BrownMember for 14 years 6 months
Created
1
1
0

I was wondering what basic holidays does that include and what is the difference in the calender between a standard 5 day work week and a standard 5 day work week with basic holidays.

Thanks

1 reply

Oldest first
  1. 0
    Gary Whitehead ·

    the holiday calendar will

    the holiday calendar will typically have all relevant nation holidays marked as non-working days, plus sometimes any standard company holiday periods (e.g. in the UK the last 2 weeks of december are often included as standard holidays)