varience BL-finish

Sunil BabuMember for 15 years 11 months
Created
4
3
0

Helo Friends,

When I scheduled a project I found an activity with finish  date jun15 and  as of may 1st datadate it is showing -212 d varience in BL-finish , actual % complete of that activity is 95% why that activity showing -212days of delay..?My question is

any mistake in selecting VARIENCE BL-FINISH in delay analysis ...is it correct? 

Regards

Sunil.

4 replies

Oldest first
  1. 0
    Daniel Limson ·

    Sunil,check the details and

    Sunil,

    check the details and see what is pushing that variance to -212d delay, it may just be accidental error in your update.

  2. 0
    Raymund de Laza ·

    Hi, The discripancies maybe

    Hi,

    The discripancies maybe due to the wrong Planned Dates and/or the assigned Baseline.

     

    As an advice..... When intends to Make a New Program as Baseline, do note of the following..

    1. Make sure the Project Planned Start = Data Date
    2. Make sure that all Activities Planned Start = Early Start = Start
    3. Make sure that all Acitivites Planned Finish = Early Finish = Finish

    Then the same program shall be used as the current program for monitoring.

  3. 0
    Sunil Babu ·

    Hi Raymund,Thanks for your

    Hi Raymund,

    Thanks for your reply.

    Regards

    Sunil

  4. 0
    Sunil Babu ·

    Hi Daniel,Thanks for

    Hi Daniel,

    Thanks for reply.

    Sunil