Skip to content

Critical activities more than non-critical

Sm PumMember for 14 years 11 months
Created
2
2
0

Hi planners

I have submitted a schedule to my manager and he has returned it with following comments;

Critical Activities are more than non Critical Activities. Try to minimize these critical activities.

 

Please Advice

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi SM You can start by

    Hi SM

    You can start by removing all constraints that force criticality.

    Next check how many tasks are set ALAP - they show critical even when there have lots of float.

    After that look at what critical tasks remain and if more that 50% look to find out why -

    First review any tasks more that 20 days long

    Next check tasks with more than 1 outgoing link - are they all necessary?

    Finally there an only be one critical path - if you have more than 1 youre programme has been rigged.

    Best regards

    Mike Testro

  2. 0
    Mike Testro ·

    Hi Hall If you have a

    Hi Hall

    If you have a programme that has a start point and a clear cascade of tasks to an end point then there will be only one critical path.

    If there is more than one CP then the chances of this occurring naturally are infinitesimal - therefore the most likely answer is the programme has been rigged.

    You can of course have a number of such sectional cascades in a single programme.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?