Hi, everyone. What duration type you will choose? then what percentage type you will use to engage your duration type. Or it is

Louis HungMember for 18 years 6 months
Created
1
3
0

 

Regarding you had completed resource loading and been authorized of your baseline.
1.Fix Duration &Units
2.Fix Duration &Units/time
3.Fix units
4.Fix Units/time
Then what percentage type you usually adopt.
1.Duration
2.Physical 
3.Unit.
Actually, I am not very sure how it engage this two elements to make it work well.
Maybe you guy can provide your well experience here.
Thanks!

1 reply

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi LouisIf your schedule if

    Hi Louis

    If your schedule if resource loaded i suggest that you use Physical percentage type. The advantage is that you can spit the remaining duration and the % completion. This is particularly useful when you apply Earned Value Techniques. The disadvantage is that you have to update every single activity and apply remaining duration and % complete.  

    Johannes

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?