Resource Assignment Spreadsheet Print Help

Ryan KMember for 14 years 3 months
Created
1
5
0

Hey gang,

This seems simple but I can't find the solution. When printing from the Resource Assignment spreadsheet view, my data spans across two sheets of paper, however, the second page only shows a continuation of the data, it does not repeat the left columns, i.e. Activity ID, Activity Name etc. This can be a bit confusing when trying to match the second page up to the first to see which activity you're looking at.

Anyone know how to make this show up/print on the second sheet as well without having to export to excel?

Thanks,

RK

1 reply

Oldest first
  1. 0
    Ryan K ·

    It might help if I gave some

    It might help if I gave some info; I am using Primavera P6 Release 7.0 SP2.

Log in or join to reply